Operational Qualification (OQ) for Equipments

Qualification1
                                                                             PROTOCOL

Requirements are as follows:
a) Validation Team
b) Objective
c) Scope
d) Responsibility
e) Equipment description
f) Operation Checks:
i) Verify calibration of instrument associated with equipment
ii) Verify PLC (Programmable Logic Control) validation of equipment
iii)  Control Panel Testing to perform to verify the response of equipment at input from various switches and push button
iv) Power and Communication failure recovery: It is performed to verify the event of a power loss or communication failure, the equipment will stop in safe conditions
                                      v) Safety feature verification: It is performed to verify the safety parameters to avoid damage to equipments
g) Verification of Standard Equipment/ Master Equipment used for qualification:
                                        i) List of enclosures
                                       ii) Training Certification
                                      iii) Change control procedure
                                      iv) Qualification Certification
                                       v) Summary & Conclusion
                                      vi) Document Revision History
h) OQ report shall be complied by : Officer to Senior Executive Engineer
Checked by: Senior Executive
Reviewed by: Executive or Senior Manager QA and plant head
Approved by: QA Head
                            
i) If conclusion of protocol is not satisfactory than rectify the problem and re-perform the OQ

Copyright Notice: This Article/SOP/Compilation/Published Content is protected by Indian & International Copyright Laws. Reproduction and Distribution of the same without written permission is prohibited. Mail us at: info@pharmastate.com